Our meeting with Barratt – September 2024

On 2nd September, we met with directors from Barratt’s Building Safety Unit to discuss progress with their remediation programme. This followed our initial meeting with Barratt in November 2023 and our more recent meeting in May 2024.

Barratt has set aside more funding than any other developer to remediate homes across the UK that have life-critical fire safety defects – and the scale of work still to be done is enormous.

We discussed a wide range of topics during our meeting, which you can read about in our full report. In summary, 

• In almost every case, we were advised that the Building Safety Regulator has requested an extension to the building control approval process; this is the latest reason for delays to remediation start dates. 

• More than 160 buildings are still waiting for an assessment to determine if remediation is required. 

• In principle, Barratt would be satisfied if a building owner provided an EWS1 with an A1 rating, without proactively assuring themselves of the quality or requesting a more up-to-date assessment if it pre-dated the introduction of the current PAS 9980 standard. 

• In some cases, leaseholders have been waiting almost a year after their building assessment to hear the outcome, with no rationale for the delay. 

• Barratt intends to remediate buildings to the minimum standard required by the developer contract, which may result in combustible materials remaining on the external wall if the risk is deemed tolerable (a “B1” rating) – regardless of whether they receive a “barrage” of complaints from leaseholders and residents. 

• In multiple cases, leaseholders do not yet have an assurance from Barratt that they will not be charged for fire door surveys and remediation, even if there is a 100% failure rate which indicates an original defect. 

• In light of the recent Dagenham fire, which starkly highlighted the additional safety risks for residents who are forced to remain in their homes during remediation works, we raised resident concerns about whether Barratt was committed to the Remediation Code of Practice. 

• Our report also highlights the additional money Barratt has had to set aside for fire safety remediation, and we review what the latest government data tells us about the progress of their remediation programme. 

Read the full report on our meeting with Barratt here. 

CALL TO ACTION! 
Are you a leaseholder or resident in a Barratt building, having issues in relation to assessment or remediation – and unable to get a satisfactory response via your managing agent? Please email the developer directly at ewsenquiries@barrattplc.co.uk and copy us at endourcladdingscandal@gmail.com if you would like us to be aware of the issues being raised and to follow up if needed.  

If you need to escalate your concerns to MHCLG, please email building.safety@communities.gov.uk, providing the name and address of your building together with a short summary of your concerns, and detailing the attempts you have made to contact the developer. Please copy our team at endourcladdingscandal@gmail.com so that we can follow up where necessary.

End Our Cladding Scandal

Follow us on Twitter
for important updates on the campaign, ways to get involved and new information

Find out more about the End Our Cladding Scandal Campaign

You Might Also Like